Investment Review
Conversion Contracts
As of end-July, overall Hilli FLNG 
project progress remained on schedule and expenditure for the quarter 
was in accordance with the approved budget. During the quarter sponson 
construction, assembly, blasting and painting work progressed.  
Fabrication of piping and pipe supports continued and good progress was 
made with the repair and life extension work for the vessel. Significant
 activities undertaken during the last quarter included addressing 
specific design and operation issues (Perenco/Cameroon) and the overall 
project at the end of July is calculated to be 60% complete.
On July 21,
 the Company executed agreements for the conversion of the 126,000m3 LNG
 carrier Gandria to a Golar floating liquefaction facility (GoFLNG). The
 Gandria conversion will now be dedicated to satisfy the commitments to 
Ophir in Equatorial Guinea, covered by the agreement announced in May 
this year, requiring delivery of facilities in 2019. This move will 
release the Gimi (conversion contract signed in December 2014) to cover 
the potential emerging demand for a 2018 GoFLNG project. Provisions in 
the Gimi and Gandria contracts give Golar the flexibility to adjust 
project timing and to limit expenditure. The objective for Golar is to 
ensure that it does not remain financially exposed in any material 
manner to more than one speculative GoFLNG. Golar's ability to deliver 
fast track GoFLNG solutions by having a pipeline of key long-lead 
components on order is a critical part of the business strategy.
The Gandria conversion contract is on
 target to become effective by the end of September this year. This 
contract provides similar beneficial cancellation provisions, which if 
exercised before December 2016 will allow termination of the contracts 
after deduction of a set cancellation fee.
GoFLNG - Business Development Progress
Agreement has now been reached with 
the support of the Boards of both Golar and Perenco on the material 
commercial terms and conditions for the approximate 1.2 million tonne, 
8-year Cameroon FLNG project scheduled to commence operations in 2Q 
2017. The Tolling Agreement which defines the material commercial terms 
and conditions for the project is now subject to finalisation with SNH. 
The Midstream Gas Convention setting out the regulatory and fiscal 
regime governing the FLNG operations in Cameroon is now only subject to 
finalisation with the government. All parties including the government 
of Cameroon remain on track and are confident of approving the Tolling 
Agreement and the Midstream Gas Convention by the end of September 2015.
 Signing of these agreements will formalise FID for Golar's first GoFLNG
 project.
The Company expects the project in 
Cameroon to deliver an EBITDA for Golar in the first full year of 
operation, based on the utilisation of 2 of the available 4 liquefaction
 trains, in the range of $170 million to $300 million, with a flexible 
tolling structure which correlates to Brent crude oil prices ranging 
from a floor of $60/bbl to a cap of $102/bbl.
Golar announced on May 5
 that it had signed a binding Heads of Terms with Ophir Energy Plc for 
the provision of the GoFLNG vessel Gimi or alternate. Subsequently the 
Gandria was nominated for the Equatorial Guinea project so that Gimi can
 be available in time for potential GoFLNG projects starting operations 
in 2018. The agreement for Gandria will be structured as a 20-year 
tolling contract, commencing commercial operations in the first half of 
2019.
Golar, with its partners Keppel 
Shipyard and Black & Veatch, committed to the Gimi FLNG conversion 
in December 2014. Gimi and Gandria will both benefit from utilising the 
same configuration of utilities and liquefaction facilities as sister 
ship Hilli, with variations to Gandria to accommodate production direct 
from the deep-water reservoir. During the quarter, additional detailed 
engineering studies (FEED) were commenced for Gandria with the objective
 of finalising the design and budget for the deep water variations. The 
integrated Ophir/GEPetrol/Sonagas/Golar project remains on schedule to 
take FID during the first half of 2016.
The Cedar LNG Project development 
activity for the quarter included continued support of the NEB LNG 
export application as well as focus on solidifying arrangements for gas 
transportation service into the Douglas Channel area. The Company 
continues to monitor development activities for the relevant large scale
 pipeline projects upon which the first phase of Cedar LNG is dependent.
 Golar is currently anticipating FID for Cedar Phase I to be achieved by
 the end of 2016 assuming such third party pipelines maintain their 
current schedules.
New GoFLNG business development 
activity has been focused on maturing projects that have the potential 
to commence operations in 2018. A shortlist of 4 potential projects is 
currently subject to active discussions. Interestingly, each of these 
projects is located in a completely separate geographic region. In each 
of these projects the competitive tolling fees and flexible commercial 
structures have the potential to generate very attractive economics, 
even at today's low oil and LNG prices.
To meet potential customers' demand 
for early commencement, Golar has initiated discussions with Keppel 
Shipyard and Black & Veatch. The target is to achieve a fourth 
conversion with a delivery in late 2018/early 2019. A commitment will be
 dependent on Golar firming employment opportunities within 1Q 2016.
The recent weakness in oil and gas 
prices has highlighted the benefits of a fast track FLNG solution versus
 large, capital intensive greenfield LNG developments. In addition to 
reduced capital expenditure and accelerated start up, the Company's 
counterparts appreciate the flexibility the floating toll creates with 
respect to term and volume. Several of the business opportunities 
currently being discussed are based on stranded, associated or flared 
gas with limited commercial value without monetization through LNG 
production.
Capital expenditure for new, large 
scale Greenfield LNG developments shows a cash breakeven level from $10 
per mmbtu and upwards. The cash breakeven level for a turnkey GoFLNG 
development can be significantly lower.
The Company is confident that a 
GoFLNG solution supplied with African or Asian gas reserves generates a 
reasonable return both for producers and Golar even with European and 
Asian gas prices at current levels. Significant upside can be monetized 
if gas prices recover. Golar is further confident that with respect to 
feed gas price, capital cost, transportation cost and flexibility, it 
has a competitive advantage over US export projects.
FLNG financing
As at June 30,
 including the value of the original vessel, Golar has invested $411 
million in the Hilli conversion project. Today this investment sits at 
$424 million.  From the end of September when the tolling agreement and 
the midstream gas convention have been approved by SNH and the Cameroon 
government, respectively, all remaining conversion and site specific 
costs for the GoFLNG Hilli will be satisfied by a fully documented and 
underwritten facility provided by CSSC (Hong Kong) Shipping Co. Ltd. 
("CSSCL"). This will fund up to 80% of the GoFLNG Hilli.
The financing structure will be split
 into two phases. Phase one enables Golar to draw down up to $700 
million from the facility to fund the ongoing project cost once Golar 
and its minority partners have spent $400 million of the estimated 
$1.2bn project cost. Phase two is triggered upon delivery of the 
converted GoFLNG Hilli from Keppel Shipyard and the satisfaction of 
certain milestones.  This will provide for the drawdown of a further 
$260 million giving an aggregate $960 million.  This final tranche is 
expected to satisfy the remaining conversion costs outstanding at that 
time and the remainder will be a release of the Company's equity.
The CSSCL financing has a tenor of 
10-years, a 15-year amortisation profile and contemplates the eventual 
sale of GoFLNG Hilli to Golar Partners.  The expected cost of the 
financing during the conversion period is 6.25% while the long term 
financing is projected to cost less than 6% on a fully swapped ten year 
basis.
Liquidity
The Company maintains a good 
liquidity position notwithstanding the current weak operating results. 
The cash balance at the end of 2Q is $375 million and a further $100 
million is receivable from Golar Partners in respect of the Eskimo sale.
 Additionally, the Company will receive $50 million in yearly 
distributions from Golar Partners. The capital expenditure for Gimi and 
Gandria over the next twelve months is to a large extent dependent on 
progress with contractual employment discussions. As at June 30, 2015, 
$50 million has been invested in the Gimi and Gandria conversions.  If 
no progress is made firming up employment opportunities, the total cash 
expenditure will have increased to $65 million for these two vessels in 
the period up to June 30, 2016, of which $30 million is recoverable in the case of termination.
Corporate and other matters
The recent collapse of oil and gas 
prices has increased interest in LNG fueled combined cycle power 
generation. A shortage of power in areas like Brazil, Indonesia, India 
and South Africa and strong power prices in these areas together with 
lower gas prices have dramatically improved the economics of gas fuelled
 power generation.  Simultaneously, we see stranded and associated gas 
reserves that can be acquired at attractive valuations. The lack of near
 term liquidity in the LNG market to a certain extent prevents resource 
holders from developing reserves before they have firm off take 
contracts.
In order to develop Golar further and
 accelerate the implementation of the GoFLNG concept, the Company has in
 recent months been negotiating with Brazilian power partners. These 
partners have been awarded a 25 year PPA contract with Brazilian 
authorities to build and operate a 1.5 GWha LNG fuelled combined cycle 
power station in Sergipe, Northern Brazil. Golar has negotiated a right 
to participate in up to 25% of this project and has the exclusive right 
to provide the FSRU. In addition to supplying the power station with 
gas, the FSRU would also have excess capacity to deliver gas to the 
Brazilian grid. The partners are currently working through the 
permitting process and are in negotiations with LNG providers, 
contractors and financiers. The capacity payment achieved in the PPA 
contract was awarded at a historically high level. If Golar proceeds, it
 would do so on the basis of an expected unleveraged project return in 
excess of 15 %. Further upside is available based on usage.
Golar intends to establish a 
stand-alone, non-recourse subsidiary, Golar Power Ltd. to hold this 
investment. The Company's total commitment to this subsidiary will 
initially be $5 million in liquidity lines and $24 million in 
non-performance guarantees, effective from 2020. Further equity 
investments would be needed if the project gets a final go ahead. It 
would be Golar's intention to bring additional partners into Golar 
Power. In addition to the solid project return, Golar would use this 
position to accelerate its GoFLNG activities by creating a natural 
partnership with power producers and traders. The target is to offer a 
more integrated LNG solution to resource holders.  Golar has approached 
several leading trading companies with this idea and has received 
encouraging feedback. A final clarification around this structure should
 be expected before year-end.
The size of Golar's investments in 
Golar Power will be relatively small compared to the Company's 
commitment to FLNG, FSRUs and LNG shipping. Golar's business model 
remains to be a midstream gas company focussed on tariff based FLNG 
production. It is the Company's intention to separate Golar Power from 
the rest of the activities over time. This can take place through a spin
 off to Golar's shareholders.
 
 
 
 Posts
Posts
 
 
 
 
 
 
 
 
 
No comments:
Post a Comment